Gianforte Hall Construction Progress

Summer 2024 Photos

September 9 September 4 August 27
August 20 August 13 August 8
August 6 July 26 July 17 - concrete foundation footer process starts
July 16- foundation forms with rebar July 9 July 5
July 1 - large rainfall must be eliminated June 27 June 24
June 20 - digging out foundation June 18 June 13
June 10 June 6 - drilling footer holes June 3 - initial site preparation